Magna Mining said on November 12 that it will combine Levack and the adjacent McCreedy West mine into the Levack Mine Complex in Ontario’s Sudbury Basin, sharing technical and maintenance staff as it prepares Levack for a restart.
The company expects refurbishment and recommissioning of Levack’s production hoisting system to finish in the first quarter of 2027. Shaft guides have been replaced and hoist upgrades are underway. Magna says the work will allow it to lift stockpiled development ore and waste, then accelerate underground development ahead of planned pre-commercial ore production during 2027.
In its November 12 update, Magna also said it plans to resume work on the 2950 Level exploration drift in early December. Extending the drift closer to the R2 Footwall Zone would shorten definition drill holes used for mine planning. A fourth underground drill has been mobilized to the rehabilitated 2650 Level.
The restart work comes as McCreedy West faces a lower production outlook. In its November 11 quarterly results, Magna revised 2026 guidance to 14.5 million–15.5 million payable copper-equivalent pounds after operational difficulties in the third quarter. It reported 3.7 million payable copper-equivalent pounds for the quarter and 12.3 million for the first nine months. Copper-equivalent figures combine several metals using specified prices; they do not represent copper alone.
Chief executive Jason Jessup attributed the disruption to a geological structure affecting a high-grade stope on the 910 Level. He said the issue had been resolved, but changes to the mining sequence deferred some higher-grade production into 2027.
Magna’s quarterly payable output included 1.8 million pounds of copper, alongside nickel, platinum, palladium, gold and silver.

This brief is based on Magna Mining’s announcement of November 12, 2026. Company statements and forecasts are attributed to their source. This is a summary of the announcement, prepared by Mining Brief, rather than independent on-site reporting.