Vancouver-based Newcore Gold said on November 19 that it had submitted a mining lease application for its Enchi gold project in southwestern Ghana. The application covers 53.37 square kilometres within the company’s 248-square-kilometre property.
The company expects the review to finish by mid-2027. In a statement included in Newcore’s announcement, Ghana’s lands and natural resources minister, Emmanuel Armah-Kofi Buah, set out a goal of granting the lease in the first half of 2027. Those dates remain targets; the announcement reports an application, rather than an approval.
Newcore said it could formally apply to Ghana’s Environmental Protection Authority for an environmental permit once the mining lease is granted. It plans to support that next application with monitoring and baseline work undertaken since 2015, including studies completed this year.

The filing follows a pre-feasibility study announced on June 24 that Newcore said would underpin its lease application. That study evaluated an open-pit operation using contract mining and a central mill processing 5.5 million tonnes a year. Its estimated upfront capital cost was US$351 million, with a 24-month construction period.
The study projected average annual output of about 104,000 ounces over a 9.3-year mine life. Ore would come from four deposits: Boin, Sewum, Nyam and Kwakyekrom. These are study estimates for a proposed operation, rather than production results.
This brief is based on Newcore Gold’s announcement of November 19, 2026. Company statements and forecasts are attributed to their source. This is a summary of the announcement, prepared by Mining Brief, rather than independent on-site reporting.