Lithium Americas lifts Thacker Pass cost estimate to US$3.83 billion

The Canadian company raises its Nevada lithium project estimate while retaining a late-2027 mechanical completion target.

Roads and earthworks at Thacker Pass in a radar satellite image
Thacker Pass roads and earthworks in a radar satellite view. Archive image, January 13, 2025; not current construction. Image: Umbra Lab, Inc. / Wikimedia Commons, CC BY 4.0. Contrast enhanced, reduced and converted to JPEG; recompressed by Ghost; further delivery changes possible. Photo source ↗ Photo licence ↗ View full-size image

Lithium Americas has raised the estimated capital cost of the first phase of its Thacker Pass lithium project in Nevada to US$3.83 billion, including contingency. The Vancouver-based company confirmed the figure in its November 12 quarterly results, following a project update a day earlier.

The previous estimate was US$2.93 billion. The increase is about 31%, calculated from the two rounded figures. Lithium Americas still targets mechanical completion in late 2027 and a production ramp-up through 2028; those dates remain company forecasts.

In its November 11 update, the company attributed the higher estimate to several pressures beyond tariffs. It identified about US$245 million in additional costs tied to installation rates for piping, steel and equipment, US$150 million for craft wages and compensation, and US$150 million for engineering and contractor staff wages. Tariffs and logistics together accounted for about US$100 million, while additional staffing and contingency also contributed.

The funding requirement is broader than the construction-cost increase. In the quarterly results, Lithium Americas put the additional requirement at approximately US$995 million, including changes to reserve accounts and other assumptions. It expects company contributions and access to existing U.S. Department of Energy loan reserves to cover it. The company said its contributions would increase its ownership in the joint venture and that it was working with the department and General Motors to finalize the implications for their interests.

Construction continues in Humboldt County. The November 11 update reported approximately 1,900 people on site as of September 30, with about 2,200 expected by year-end. Detailed engineering was complete and procurement was more than 90% complete, the company said.

Phase 1 is designed for a nominal 40,000 tonnes of battery-quality lithium carbonate a year at full capacity. That is planned output after construction and ramp-up, rather than current production.

SOURCE & CONTEXT

This brief is based on Lithium Americas’s announcement of November 12, 2026. Company statements and forecasts are attributed to their source. This is a summary of the announcement, prepared by Mining Brief, rather than independent on-site reporting.