Tartisan Nickel has received an early exploration permit for its Turtle Pond nickel-copper-cobalt project near Dryden in northwestern Ontario, clearing a regulatory step for a proposed 2,880-metre drill program. Ontario issued the permit on November 17; the company announced it on November 19.
The provincial decision names Canadian Arrow Mines, Tartisan’s wholly owned subsidiary, as the proponent. Permit PR-26-000146 allows mechanized drilling with equipment weighing more than 150 kilograms. The registry also lists a geophysical survey requiring a generator among the planned activities and says the permit can run for up to three years, with possible renewal.
Tartisan’s proposed program divides 14 diamond drill holes into two phases. Six holes totalling about 1,060 metres would revisit the Double E, Night Danger and Glatz showings. The company wants to check selected historical holes and obtain fresh core for possible metallurgical testing.

The other eight holes, totalling about 1,820 metres, would investigate electromagnetic conductors, magnetic anomalies and possible extensions of known mineralization. Tartisan says those targets draw on geophysical surveys completed in 2024 and 2025.
The permit does not establish a drilling start date. Tartisan says the work still depends on financing, contractor availability, permit conditions and any further authorizations. Hole locations and the number of metres may change as crews collect field information.
The registry’s public comment period ran from September 4 to October 4. Ontario recorded no comments through the registry, email or mail. Its notice says the permit does not remove obligations under other legislation, and exploration must meet provincial standards.
This brief is based on Tartisan Nickel’s announcement of November 19, 2026. Company statements and forecasts are attributed to their source. This is a summary of the announcement, prepared by Mining Brief, rather than independent on-site reporting.